← PROJECTS · Phase 8 of 9
Phase 8 · 3–7 days
Go Live
upcoming
Permission to Operate granted. Your system energizes for the first time. Your Energy Architect calls you the moment your panels produce their first watt.
Your tasks
- Confirm receipt of your PTO notification
- Attend commissioning walkthrough — approximately 30 minutes
- Download & configure your system monitoring app
- Review your Homeowner Operations Guide
Seamless Home tasks
- PTO application submission to utility
- Net Metering enrollment confirmation
- System energization & live performance test
- Production vs. modeled output verification
- Monitoring system activation & alert setup
- Commissioning walkthrough with homeowner
- Final documentation package delivery
Documents
Permission to Operate (PTO) Letternot started
Net Metering Enrollment Confirmationnot started
System Commissioning Reportnot started
Monitoring System Setup Guidenot started
Conditional Final Lien Waivernot started
Homeowner Operations Manualnot started
Note
This is the moment everything has been building toward. Your Energy Architect calls you personally when your system produces its first watt.
Tip
Average time from install to PTO in California is 14–21 days, depending on your utility interconnection queue.